Capitola City Council · Thursday, October 8, 2026, 6:00 PM · Item C · Consent Items

MinorTransportation & traffic

Accept finished Reposa Avenue paving work and release $6,800 held back

In plain English

The Council would accept the 2026 Reposa Avenue Pavement Rehabilitation Project as complete, done by Betz Works Inc. at a final cost of $151,000, file and record a Notice of Completion, and release the $6,800 contract retention held under the construction agreement.

Official wording

Notice of Completion for Reposa Avenue Recommended Action: 1) Accept as complete the 2026 Reposa Avenue Pavement Rehabilitation Project completed by Betz Works Inc. at a final cost of $151,000; 2) authorize the City Clerk to file and record a Notice of Completion; and 3) authorize the release of the contract retention $6,800 as prescribed in the construction agreement.

Summary written by claude-opus-5 from the agenda. It can contain mistakes. The official documents govern.