Capitola City Council · Thursday, October 22, 2026, 6:00 PM · Item B · General Government / Public Hearings
Pick an engineering firm for Stockton Avenue Bridge maintenance work
In plain English
The City Council is being asked to hire an engineering firm to design maintenance repairs for the Stockton Avenue Bridge, which carries Stockton Avenue over Soquel Creek between Wharf Road and Esplanade. The main recommendation (Option 1) is a contract with Moffatt & Nichol for up to $146,000 to design a polyester concrete overlay on the bridge deck, clean the abutment joints, repair the asphalt approach, overlay the roadway, and prepare bid-ready plans, plus bid and construction support. Option 2 would instead hire Mark Thomas for up to $125,428. Either option would also amend the budget to take the money from restricted road funds. This hires the designer only; the actual construction work would come back to Council later for more money and approval.
Stockton Avenue Bridge is the only local road crossing Soquel Creek south of Highway 1, and the design assumes a full closure to vehicles between Wharf Road and Esplanade with traffic detoured to the Highway 1 interchanges at 41st Avenue and Bay Avenue during construction. Paying for the design out of restricted road revenue would cut money set aside for future street paving from about $275,000 to roughly $129,000.
Key facts
- Three firms bid: Mark Thomas $125,428, Moffatt & Nichol $146,000, Kimley-Horn $146,350. A fourth firm declined as the work was outside its expertise.
- The recommended Moffatt & Nichol agreement is $132,000 for design plus a $14,000 allowance for bid and construction support — $20,572 more than Mark Thomas.
- The $146,000 would come from about $275,000 in restricted road revenue budgeted for FY 2026–27, leaving roughly $129,000 for future pavement projects.
- A preliminary overlay construction estimate of about $284,000 (excluding traffic control and approach-roadway work) plus the engineering contract totals roughly $430,000, before inspection, testing and contingency.
- Moffatt & Nichol expects about 12 weeks to produce final bid documents after notice to proceed, excluding City and agency review time; the bridge was built in 1934 (Bridge No. 36C0110).
Reasons to support
- Staff say a qualified bridge engineer must set repair limits and prepare bid-ready plans, specifications and an estimate before construction can even be put out to bid, as reported to Council on September 10, 2026.
- Moffatt & Nichol received the highest overall rating, has worked on this specific bridge (engineering and permitting for the 2023 pier wall emergency repairs and a deck repair review), and has retrofitted historic concrete arch bridges on Highway 1 in Monterey County.
- The polyester concrete overlay would put a protective surface on the deck to slow deterioration and buy time until a long-term rehabilitation or replacement project can be identified, funded and built.
Reasons to oppose or change it
- Mark Thomas was also found qualified and would cost $20,572 less; it reports delivering more than 100 Highway Bridge Program projects, offers grant and funding assistance, and was recently hired by the City for the Capitola Trestle assessment.
- The money comes from restricted road revenue that was intended to build reserves for future pavement projects, cutting that reserve to about $129,000, and the assignment was not in the FY 2026–27 five-year Capital Improvement Program or operating budget.
- Staff note the overlay would not replace the deck or fix the bridge's long-term deficiencies, about $350,000 has already been spent on bridge investigations, the $500,000 long-term bridge grant cannot be used here, and construction, inspection and materials testing would all be additional costs requiring another Council authorization.
Official wording
Stockton Avenue Bridge Maintenance Engineering Services Recommended Action: Option 1: Authorize the City Manager to execute a Professional Services Agreement, in a form acceptable to the City Attorney, with Moffatt & Nichol for Stockton Avenue Bridge maintenance engineering services, including bid and construction support, in an amount not to exceed $146,000; and approve a budget amendment appropriating $146,000 from available restricted road funds for these services. Option 2: Select Mark Thomas and authorize the City Manager to finalize an agreement in an amount not to exceed $125,428, with the corresponding budget amendment.