County Board of Supervisors · Tuesday, November 10, 2026, 9:00 AM · Item 36 · AUD61 - CSA 7 - Z2
$85,000 more for tree work under 2026 hazard mitigation grant project
In plain English
The County hired Core Tree Care, LLC to clear wildfire fuel along eight County-maintained roads — up to 50 miles of brush and vegetation removal to make evacuation routes safer. After the contract was awarded, the County confirmed that the federal environmental review requires an archaeologist to be present and to report during the work, because 17 historic features (existing roads, culverts, bridges and similar transportation structures) are in the project area. A yes vote approves paying the contractor an additional $85,000 for that archaeological monitoring, training and reporting, and raises the project's contingency (set-aside for unexpected costs) to $120,000.
The work is meant to improve evacuation safety on eight County-maintained roads during wildfire, and this change order decides whether the project proceeds now on schedule or waits while the County seeks different environmental terms, which staff say could substantially delay construction.
Key facts
- Change Order No. 1 Supplemental 1 with Core Tree Care, LLC is for $85,000; an earlier $35,000 change order was already executed to start archaeological assessments and training.
- Archaeological monitoring costs $2,000 per working day, estimated at 60 working days, for a total estimated $120,000.
- The revised contingency of $120,000 is the original contingency of $45,390.80 plus an additional $74,609.20.
- Core Tree Care, LLC was the low bidder at $453,908.00; the construction contract including all add alternates is $538,908.00, and total estimated project cost is $1,176,399.
- Funding: up to $989,762 from the Federal Emergency Management Agency's Hazard Mitigation Grant Program, plus local match of $80,000 from Measure Q and $250,000 from Measure K.
Reasons to support
- The federal environmental review found "No Adverse Effect to Historic Properties" only on the condition that archaeological monitoring occurs, so the monitoring is required to keep the grant-funded project in compliance.
- Staff coordinated with the Federal Emergency Management Agency, the California Governor's Office of Emergency Services and the project archaeologist and found no alternative monitoring approach; changing the consultation would require more environmental review and could substantially delay construction.
- Seasonal environmental restrictions and grant deadlines make delay costly, and the Federal Emergency Management Agency has indicated archaeological monitoring is an eligible expense, so much of the cost may be grant-covered.
- Payment is based on monitoring actually provided, so if construction finishes in fewer days the County pays less than the $120,000 estimate.
Reasons to oppose or change it
- Federal reimbursement is not yet secured — the Federal Emergency Management Agency's eligibility statement is "subject to the required scope and budget modification," which the County is still pursuing while the work goes forward.
- The project is mainly vegetation removal with no anticipated ground disturbance, yet it must pay $2,000 per working day for an archaeologist to be on site, a requirement that was missed when the contract was advertised in April 2026.
- The contingency more than doubles, from $45,390.80 to $120,000, and local match dollars at stake include $80,000 from Measure Q and $250,000 from Measure K if grant coverage falls short.
- Staff identified an alternative — pause construction and seek revised environmental consultation — which was rejected on schedule grounds rather than cost.
Official wording
Approve Contract Change Order No. 1 Supplemental 1 with Core Tree Care, LLC in the amount of $85,000 for 2026 Hazard Mitigation Grant project, approve revised contingency amount of $120,000, and take related actions (Community Development and Infrastructure - Public Works)
Summary written by claude-opus-5 from the agenda and the Staff Report. It can contain mistakes. The official documents govern.