County Board of Supervisors · Tuesday, November 17, 2026, 9:00 AM · Item 15 · CONSENT AGENDA
Easement purchases for Highway 1 bus-on-shoulder and rail trail work
In plain English
The County has negotiated deals to buy easements — rights to use parts of three private properties — needed to build the Highway 1 Bus-on-Shoulder Segment 3 and Rail Trail Segment 12 Project. A yes vote approves the purchase contracts, lets the General Services Director sign them, lets the Board Chair sign the easement deeds, authorizes payment to the property owners, and accepts $186,800 from the Santa Cruz County Regional Transportation Commission to cover the cost. The easements include temporary access and construction rights during building, plus permanent trail easements.
Three private property owners would be paid fair market value for use of portions of their land, and the project — a new bus-on-shoulder lane on Highway 1 plus a new Rail Trail segment — cannot proceed without these property rights.
Key facts
- Total acquisition cost: $186,800, fully reimbursed to the County by the Santa Cruz County Regional Transportation Commission.
- $25,600 for a temporary easement over a portion of APN 044-282-34, owned by George Brothers, Jr.
- $100,000 for a temporary construction easement over a portion of APN 039-471-10, owned by Redwood Coast LLC.
- $61,200 for temporary construction easements and permanent trail easements over portions of APNs 041-042-11 and 041-052-17, owned by Saundra Bowersock Ruso.
- On December 12, 2023, the Board approved a Cooperative Agreement under which the County's Real Property Division handles land acquisition for the Regional Transportation Commission on this project.
Reasons to support
- The payments are based on professionally appraised fair market value, and the Regional Transportation Commission reimburses the County for the full acquisition cost and associated staff time.
- The easements are required for the project to proceed; staff describe the project as expanding transportation and mobility options, reducing traffic congestion, and building a new Rail Trail segment next to Highway 1.
- The contracts were negotiated with the owners rather than imposed, and the amounts exceed the General Services Director's delegated authority, so Board approval is the required next step.
Reasons to oppose or change it
- Approval commits portions of three private properties to permanent trail easements and construction use; owners who disagree with the appraised values or the loss of land use have this vote as the decision point.
- The three parcels are valued very differently — $100,000 for one temporary construction easement versus $25,600 for another — and the staff report gives the appraisals as the only basis for those differences.
- Because the item is on the consent agenda, the contracts would be approved in a single bundled vote without separate discussion unless a supervisor pulls it.
Make your voice heard
Pick a side and we'll draft a short email to BoardOfSupervisors@santacruzcountyca.gov that you can edit and send from your own account. Emails to the body become part of the public record.
How to take part
Show up: Tuesday, November 17, 2026 at 9:00 AM, Board Chambers, 701 Ocean Street, Room 525, Santa Cruz. California's open-meetings law (the Brown Act) gives you the right to speak on agenda items. Remote-participation links, when offered, are on the agenda.
Write in: BoardOfSupervisors@santacruzcountyca.gov (from County of Santa Cruz Board of Supervisors agenda, 2026-09-15 ("Submitting Related Correspondence"))
Deadline: Written comments must be received before 5:00 p.m. the day before the meeting to be included with agenda materials. Comments received after that, until the end of the meeting, go into the minutes record.
Include the agenda item number. You can also comment on individual items with the "Add Comment" tool on the Board's meeting portal.
Official wording
Approve terms and conditions of easement acquisition contracts for the Highway 1 Bus-on-Shoulder Segment 3 and Rail Trail Segment 12 Project, and take related actions (General Services Department)
Summary written by claude-opus-5 from the agenda and the Staff Report. It can contain mistakes. The official documents govern.