County Board of Supervisors · Tuesday, November 17, 2026, 9:00 AM · Item 18 · CONSENT AGENDA

MajorTransportation & traffic, Planning & development

County consent for rail trail agency to use eminent domain for Segment 12 land

In plain English

The county's Regional Transportation Commission needs strips of land from six privately owned parcels to build Coastal Rail Trail Segment 12, a roughly 1.25-mile bike and walking path along the Santa Cruz Branch Rail Line between State Park Drive and Rio Del Mar Boulevard. Under state law, the Commission can only use eminent domain (forcing a sale at a court-determined price) inside the rail corridor in the unincorporated county if the Board of Supervisors first consents by resolution. A yes vote gives that consent for portions of Assessor's Parcel Numbers 042-011-06, 044-282-47, 044-282-48, 041-561-04, 041-011-55, and 041-011-35. It does not set any payment amounts, and county staff say they will keep negotiating voluntary purchases at the same time.

Owners of the six listed parcels along the rail corridor could have portions of their land taken through condemnation rather than a voluntary sale, while trail users and Highway 1 travelers are affected by whether the project stays on schedule to keep $180 million in grant funding.

Key facts

  • Consent would cover portions of six parcels: Assessor's Parcel Numbers 042-011-06, 044-282-47, 044-282-48, 041-561-04, 041-011-55, and 041-011-35.
  • The trail segment is approximately 1.25 miles of bicycle and pedestrian facilities between State Park Drive and Rio Del Mar Boulevard.
  • The Commission says it must adopt Resolutions of Necessity now to support Right-of-Way Certification 3W and meet deadlines tied to $180 million in grant funding.
  • Government Code section 67941(a) gives the Commission eminent domain power in the rail right-of-way but requires the Board of Supervisors to consent before it files an action in the unincorporated county.
  • Staff have negotiated with property owners over the past 18 months; the Commission will fund staff time and acquisition costs, with county-advanced payments reimbursed under Cooperative Agreement Doc-2023-1027, approved by the Board on December 12, 2023.

Reasons to support

  • Without the consent resolution, the Commission cannot move forward with Resolutions of Necessity, which staff say are needed to certify the right-of-way and preserve $180 million in grant funding.
  • The trail is part of a larger Highway 1 project that adds auxiliary lanes, bus-on-shoulder improvements, two replacement railroad bridges and a widened bridge over Aptos Creek and Spreckels Drive, and staff say the trail will improve bicycle and pedestrian safety and connections to schools, shops and transit.
  • Consent does not end negotiations: staff will keep pursuing voluntary agreements in parallel, with the stated goal of never filing a condemnation case.

Reasons to oppose or change it

  • Consenting to condemnation removes the owners' ability to simply say no; after 18 months of negotiation, the remaining six parcel owners could have land taken at a price set through court proceedings rather than agreement.
  • The grant deadline pressure means the Commission is starting the forced-acquisition process before negotiations have concluded, which reduces owners' leverage in the remaining talks.
  • The Board is consenting without knowing the compensation: the item approves no specific amounts, and final payments will be determined later through negotiation or eminent domain proceedings, with the county advancing some costs subject to reimbursement.

Make your voice heard

Pick a side and we'll draft a short email to BoardOfSupervisors@santacruzcountyca.gov that you can edit and send from your own account. Emails to the body become part of the public record.

How to take part

Show up: Tuesday, November 17, 2026 at 9:00 AM, Board Chambers, 701 Ocean Street, Room 525, Santa Cruz. California's open-meetings law (the Brown Act) gives you the right to speak on agenda items. Remote-participation links, when offered, are on the agenda.

Write in: BoardOfSupervisors@santacruzcountyca.gov (from County of Santa Cruz Board of Supervisors agenda, 2026-09-15 ("Submitting Related Correspondence"))

Deadline: Written comments must be received before 5:00 p.m. the day before the meeting to be included with agenda materials. Comments received after that, until the end of the meeting, go into the minutes record.

Include the agenda item number. You can also comment on individual items with the "Add Comment" tool on the Board's meeting portal.

Comment online on the meeting portal

Official wording

Adopt resolution consenting to the Santa Cruz County Regional Transportation Commission using eminent domain to acquire property for Coastal Rail Trail Segment 12, Highway 1 State Park Drive to Freedom Boulevard Project (General Services Department)