County Board of Supervisors · Tuesday, November 17, 2026, 9:00 AM · Item 28 · CONSENT AGENDA

NotableParks, arts & recreation, Transportation & traffic

$296,012.07 engineering contract for Shark Fin Cove beach parking lot improvements

In plain English

The county would hire Bowman & Williams, an engineering firm based in Santa Cruz, under Contract No. 27D1310 for $296,012.07 to design improvements to the parking lot at the Shark Fin Cove beach access. That payment covers design work up to the 60% stage, due by summer 2027, which is what a $350,000 Coastal Conservancy grant requires. A yes vote approves the contract and lets the Deputy CEO/Director of Community Development and Infrastructure, or a designee, sign it.

Shark Fin Cove is a popular coastal beach access along the North Coast, and this contract starts the engineering and permitting work needed before any parking lot improvements can be built.

Key facts

  • Contract No. 27D1310 with Bowman & Williams of Santa Cruz for $296,012.07, covering design through the 60% stage by summer 2027.
  • Bowman & Williams' full proposal to reach 100% design and permitting, making the project ready for construction, is $513,009.52.
  • Funding so far: a $350,000 Coastal Conservancy grant plus an initial $100,000 from the Measure K District Sales Tax allocation committed by Third District Supervisor Cummings.
  • Total estimated cost of the 60% design phase is $450,000: $333,014 for the contract including departmental overhead and $116,986 for engineering oversight; oversight costs before overhead will not exceed $92,934.
  • On September 29, 2026, the Board deferred awarding this contract so staff could negotiate with the top-ranked firm, MGE Engineering of Sacramento.

Reasons to support

  • Bowman & Williams can complete the 60% design within the money the Coastal Conservancy grant provides, while the top-ranked firm, MGE Engineering, could not.
  • Reaching the 60% design milestone positions the county to apply for another Coastal Conservancy grant to finish design and obtain permits, so the project becomes shovel-ready.
  • The firm is local to Santa Cruz, and the work will be coordinated with Caltrans, the Coastal Conservancy, and local stakeholders as design proceeds.

Reasons to oppose or change it

  • This contract only gets the project to 60% design; finishing design and permitting would cost roughly another $217,000 of the $513,009.52 total proposal, and that money depends on winning a future grant that is not yet awarded.
  • The firm selected is the second-ranked consultant rather than the top-ranked one, with cost rather than ranking driving the switch.
  • Beyond the consultant fee, the county expects to spend up to $116,986 on in-house engineering oversight, bringing the 60% design phase to $450,000 against $450,000 in grant and Measure K funds, leaving no cushion for overruns.

Make your voice heard

Pick a side and we'll draft a short email to BoardOfSupervisors@santacruzcountyca.gov that you can edit and send from your own account. Emails to the body become part of the public record.

How to take part

Show up: Tuesday, November 17, 2026 at 9:00 AM, Board Chambers, 701 Ocean Street, Room 525, Santa Cruz. California's open-meetings law (the Brown Act) gives you the right to speak on agenda items. Remote-participation links, when offered, are on the agenda.

Write in: BoardOfSupervisors@santacruzcountyca.gov (from County of Santa Cruz Board of Supervisors agenda, 2026-09-15 ("Submitting Related Correspondence"))

Deadline: Written comments must be received before 5:00 p.m. the day before the meeting to be included with agenda materials. Comments received after that, until the end of the meeting, go into the minutes record.

Include the agenda item number. You can also comment on individual items with the "Add Comment" tool on the Board's meeting portal.

Comment online on the meeting portal

Official wording

Approve agreement with Bowman & Williams in the amount of $296,012.07 for Professional Engineering Services for the Shark Fin Cove Beach Access Parking Lot Improvement Project, and take related actions (Community Development and Infrastructure - Public Works)

Summary written by claude-opus-5 from the agenda and the Staff Report. It can contain mistakes. The official documents govern.