RTC Regional Transportation Commission · Thursday, November 5, 2026, 6:00 PM · Item 11 · Consent Agenda
Amend Caltrans agreement up to $2.7 million for Highway 1 lanes and Mar Vista overcrossing
In plain English
The Regional Transportation Commission is asked to let its Executive Director sign Amendment No. 4 to Cooperative Agreement 05-0419 with Caltrans, adding up to $2.7 million for "construction support" — the engineering, inspection, environmental, design and administrative work that goes with building the Highway 1 auxiliary lanes, bus-on-shoulder features and the new Mar Vista bicycle and pedestrian overcrossing between State Park Drive and Bay Avenue/Porter Street. Caltrans identified a roughly $6.7 million support shortfall; the Commission already approved $4 million of it in April 2026 and set aside the remaining $2.7 million in Measure D Highway Corridors funds in the FY 2026-27 budget at the same time. A yes vote releases that already-budgeted $2.7 million to Caltrans so support work can continue through project completion.
The money comes from Measure D Highway Corridors funds, the local sales tax dollars county voters approved for transportation, and it pays for oversight of a Highway 1 project in the Capitola/Aptos area that has run 204 working days longer than planned. Caltrans has warned that if construction claims arise during project closeout, still more capital and support funding could be needed.
Key facts
- Amendment No. 4 would add up to $2.7 million in LOCAL (Measure D Highway Corridors) funds for the construction support component of Cooperative Agreement 05-0419.
- Caltrans' analysis, based on expenditures through December 31, 2025, found a construction support shortfall of about $6.7 million; $4 million was authorized through Amendment No. 3 in April 2026 (executed July 14, 2026).
- An April 2026 staff report documented 49 contract change orders and 204 additional contract working days beyond the original 585 working days.
- As of 10/8/2026, Caltrans support costs had reached $8,595,769.00 against a $7,760,000.00 budget — $835,769.00 over — while RTC's own support costs stood at $269,722.98 of $1,000,000.00.
- The revised Funding Summary No. 05 puts the total project funding at $100,722,900, including $85,262,900 for construction capital.
Reasons to support
- RTC staff requested backup documentation from Caltrans, reviewed and verified it, and found the remaining $2.7 million request substantiated by documented increases in staffing demands, consultant usage, change orders and extended project duration.
- There is no new fiscal impact: the $2.7 million was programmed and budgeted in FY 2026-2027 after the April 2026 meeting, and signing the amendment simply releases funds already set aside.
- Caltrans confirmed in its October 2026 letter that the April 2026 cost analysis still matches what is needed to finish the job, and without the authorization the support work — inspection, engineering, environmental and administrative oversight — cannot continue to completion.
Reasons to oppose or change it
- Caltrans has already spent $8,595,769.00 against a $7,760,000.00 support budget and reports a combined overrun of $105,491.98, meaning the Commission is being asked to cover costs that have already been incurred rather than approving them in advance.
- Caltrans' own letter cautions that if construction claims arise, additional capital and support funding could still be required, so $2.7 million may not be the last request on this project.
- Every Measure D Highway Corridors dollar used to cover cost growth on this project — now roughly $6.7 million in extra support costs alone — is a dollar not available for other projects in the Measure D Highway Corridors 5-Year Program.
- The item sits on the consent agenda, so it would be approved along with other routine items unless a commissioner asks to discuss it separately.
Official wording
Approve authorizing the Executive Director to amend the construction Cooperative Agreement with Caltrans for the Highway 1 State Park Drive/Bay Avenue/Porter Street Auxiliary Lanes, Bus on Shoulder, and Mar Vista Bicycle and Pedestrian Overcrossing project for a total not to exceed $2.7 million for the construction support component of the project. (Resolution) BUDGET AND EXPENDITURES ITEMS