Santa Cruz Transportation and Public Works Commission · Monday, October 19, 2026, 6:00 PM · Item 3 · General Business
Water Street redesign would add separated bike lanes and keep north-side parking
In plain English
City staff are asking the Transportation and Public Works Commission to back a design direction for the Water Street Safety Project, which would add separated (buffered) bike lanes on Water Street between North Branciforte and Poplar Avenues. Staff recommend Option 1, which removes all 15 parking spaces on the south side of Water Street and keeps 17 of the 28 spaces on the north side, instead of Option 2, which would remove all on-street parking on both sides. Staff also recommend Option B for Poplar Avenue: a two-way bike lane on the west side between Soquel and Melrose Avenues, which removes 10 parking spaces and cuts down the number of street crossings at Water and Poplar. A yes vote recommends these two design directions to the City Council, which would consider them in early 2027.
People who bike or walk on Water Street and students walking and biking between Branciforte Middle School, Gault Elementary and nearby streets would get separated bike lanes and a changed crossing at Water and Poplar; businesses along Water Street and people who park on Poplar Avenue would lose a total of 26 on-street spaces on Water Street and 10 on Poplar Avenue.
Key facts
- Total estimated project cost of $381,000, with $342,900 from the state Highway Safety Improvement Program (Cycle 12) and $38,100 in local Gas Tax funds; funding for the Poplar Avenue improvements is to be determined.
- Over the past 10 years there were 32 collisions on Water Street between North Branciforte and Poplar Avenues, including 15 bike collisions, two pedestrian and two motorcycle collisions; nearly 50% of bike collisions were broadside.
- Option 1 cuts Water Street parking from 43 spaces (28 north, 15 south) to 17; Option 2 removes all 43. Poplar Avenue Option B cuts west-side spaces between Water and Melrose from 17 to 8, a net loss of 10.
- At a September 23, 2026 open house at Branciforte Middle School, 72 people attended; Water Street votes were 22 for Option 1 and 20 for Option 2, while Poplar Avenue drew 43 votes for Option B, 5 for Option A and 3 for Option C.
- A July 2026 parking study (two Wednesdays 11am-1pm and 4-6pm, one Saturday 11am-1pm) found 30% of on-street and 50% of off-street spaces occupied, an average of 14 cars parked on the street, and about 10% of spaces occupied 4+ hours.
- Council is expected to confirm design direction in early 2027, with a bid request in spring or summer 2027 and construction in fall 2027 to spring 2028 alongside the METRO Rapid Corridors Project.
Reasons to support
- Water Street is on the Priority Network in the 2026 Safety Action Plan, and staff note the 7% of roadways on that network account for more than half of all fatal and serious injury collisions; separated lanes target the broadside crashes that make up nearly half of the 15 bike collisions recorded.
- Parents at Branciforte Middle and Gault Elementary said the crossings at Soquel Avenue and at Water Street and Poplar Avenue keep them from letting children walk or bike to school; Poplar Option B reduces the number of crossings at Water and Poplar and was the clear favorite at the open house with 43 of 51 votes.
- Staff's parking count found an average of only 14 cars parked on the street at a time, which the 17 spaces kept under Option 1 would accommodate, and all businesses on the south side of Water Street have off-street parking lots.
- The project is paid for with grant and Gas Tax money, with no General Fund impact, no budget adjustment and no ongoing expenditure commitment.
Reasons to oppose or change it
- Option 1 still removes 26 of the 43 on-street spaces on Water Street, and some business owners objected specifically to losing spaces on the north side between North Branciforte and Stanford Avenues; businesses also said the 2-hour limits need enforcement before they can count on remaining spaces, since about 10% of spaces were occupied 4+ hours.
- Support for the alternative was nearly even at the open house — 20 votes for removing all parking versus 22 for keeping north-side parking — so roughly half of participants preferred Option 2, which would allow wider 6-foot buffers rather than the 3-foot buffers shown in Option 1.
- The recommended Poplar Avenue Option B takes 10 parking spaces from the west side between Water Street and Melrose Avenue, affecting residents and property owners whom staff have not yet consulted, and funding for the Poplar work is still to be determined.
- Open house attendees raised concerns about relocating the bus stop to the corner of North Branciforte Avenue and Water Street and about the type of separation between bike and vehicle lanes — details not yet settled in the draft plans.
Official wording
Water Street Safety Project (c402608) Motion to review draft designs for the Water Street Safety Project and recommend that the City Council approve: Design direction for Water Street that adds separated bike lanes and preserves parking on the north side of the street; and Design direction for Poplar Avenue to add a bidirectional bike lane on the west side of the street between Soquel and Melrose Avenues. Information Items Subcommittee/Advisory Body Oral Reports Items Initiated by Members for Future Agendas
Summary written by claude-opus-5 from the agenda and the Staff report (agenda packet, pages 17-22). It can contain mistakes. The official documents govern.