Scotts Valley Safety Advisory Committee · Tuesday, October 27, 2026, 2:00 PM · Item 3 · REGULAR AGENDA
Update on the city's Safe Streets for All grant
In plain English
The committee will hear an update on the City's federal Safe Streets for All (SS4A) grant application for street safety work. As described at the committee's April 23, 2026 meeting, the City submitted the application on 05/26/26, one day before the 05/27/26 deadline, for a project package presented to City Council at $11.2M in total project costs. The work comes from the City's Safety Action Plan and targets intersections with crash history, especially along Scotts Valley Dr. and Mount Hermon Rd., plus school-area demonstration projects and safety education and outreach. A yes vote or discussion here does not approve the money — the grant had not been approved as of the April report — it keeps the committee informed on status and design details.
The biggest proposed change would rebuild the Scotts Valley Dr. / Mt. Hermon Rd. intersection — the City's busiest — so drivers turning right must stop and make a 90-degree turn instead of taking a free-flowing right turn, which affects every driver, walker and cyclist using that corner.
Key facts
- Total project costs presented to City Council: $11.2M; Public Works Director Onchi noted grants of this type are usually in the $10M range while this one is for $11M, specifically for transportation.
- Grant application due 05/27/26 and submitted 05/26/26; as of April 23, 2026 it had not been approved.
- Estimated schedule: "Begin Environmental Clearance and Design" in July 2027, "Start Construction" in January 2030, and "End Construction" in June 2032.
- Typical improvements listed include high-visibility crosswalks, advanced stop bars, ADA ramps, protected bike crossings, curb radius tightening, corner islands / curb extensions, leading pedestrian intervals, No Turn on Red signs, and signal equipment upgrades; bicycle buffer lanes would be added on the Scotts Valley Dr. corridor.
- Free right turns would be eliminated at two corners: Mt. Hermon Rd. onto Scotts Valley Dr. (North) and Scotts Valley Dr. onto Mt. Hermon Rd. (West); more construction is planned near Scotts Valley High School on Glenwood Dr.
Reasons to support
- The Scotts Valley Dr. / Mt. Hermon Rd. redesign adds protective islands on all four corners so pedestrians and cyclists are more visible, especially to right-turning vehicles, which staff expect to reduce collisions.
- Police Chief Rutherford said this is the busiest intersection and he supports slowing down traffic, which is heavy on Mt. Hermon Rd., noting the impact will be mitigated by the number of lanes.
- The projects were recommended by the Safety Action Plan based on historical crash data and focus on the Scotts Valley Dr. and Mount Hermon Rd. intersections where residents raised the most concerns.
Reasons to oppose or change it
- Staff themselves named the drawback: eliminating the free right turn "may receive pushback from community members," since drivers in the dedicated right-turn lane would have to come to a full stop and make a 90-degree turn.
- Staff acknowledged added delay for right turns from Scotts Valley Dr. (West) onto Mt. Hermon Rd. and from Mt. Hermon Rd. onto Scotts Valley Dr. (North), to be offset only by signal timing changes and other unspecified elements.
- Even if funded, benefits are far off — design would not begin until July 2027 and construction would not end until June 2032, meaning years of waiting and then construction near Scotts Valley High School on Glenwood Dr.