Watsonville City Council · Tuesday, December 1, 2026, 4:30 PM · Item 9.d · CONSENT AGENDA
Add $266,100.50 to Ramsay Park Renaissance construction contract
In plain English
The City Council is asked to approve the twelfth change order on the construction contract with Robert A. Bothman Construction for the Ramsay Park Renaissance Project (No. PK-22-01), adding $266,100.50 of work. The extra work includes more hydroseed and mulch ground cover, added bilingual wayfinding signs, higher copper wire costs from price escalation, modifications to the southern access ramp to fix drainage, and a new guardrail at the parking lot where there is a steep dropoff next to a bioswale. A yes vote raises the contract to a revised amount not to exceed $29,154,270.39 and authorizes the City Manager to sign it; the money comes from the project's existing capital account (150-901-7820-15020).
Ramsay Park users would get the finishing items — bilingual signs, landscaping, a parking lot guardrail and drainage fixes on the southern access route — as the park reaches its scheduled November 22, 2026 opening, and the cost is paid from the project's already-budgeted construction funds.
Key facts
- Change Order No. 12 amount: $266,100.50; revised contract not to exceed $29,154,270.39.
- Original contract awarded March 26, 2024 for $24,530,000; the project was funded with a 10% contingency.
- With this change order, total approved change orders reach $4,624,270.39, an 18.85% increase over the original contract; excluding time extensions and major added scope, staff calculate the in-scope increase at 9.48%.
- The project was 96.3% complete as of the end of October, with a scheduled opening of November 22, 2026.
- Funding comes from Capital Improvement Project account 150-901-7820-15020; staff say remaining costs should stay within the already-appropriated project budget.
Reasons to support
- The added items address real site problems — drainage on the southern access road, and a guardrail at a bioswale where elevation changes left a steep dropoff next to paving.
- Staff say the cost stays within the 10% contingency range set when the contract was awarded and is consistent with the project being 96.3% complete, using money already appropriated.
- Added signage includes bilingual text, and the landscape revisions add ground cover as the park finishes construction.
Reasons to oppose or change it
- Change orders have now added $4,624,270.39, or 18.85%, to a contract originally awarded at $24,530,000 — above the 10% contingency originally budgeted when measured against the original contract price.
- Staff expect the full contingency to be used and flag more costs still to come for a new softball backstop, relocated irrigation north of the Ramsay Family Center, and Caltrans-requested crosswalk repaving on Main St.
- Part of this change order covers copper wiring price escalation tied to the extended schedule — a cost driven by delays rather than new park features.
- Staff note the Council could decline, in which case the proposed remaining scope would not be built and alternative details would have to be pursued.
Make your voice heard
Pick a side and we'll draft a short email to citycouncil@watsonville.gov that you can edit and send from your own account. Emails to the body become part of the public record.
How to take part
Show up: Tuesday, December 1, 2026 at 4:30 PM, City Council Chambers, 275 Main Street, Top Floor, Watsonville. California's open-meetings law (the Brown Act) gives you the right to speak on agenda items. Remote-participation links, when offered, are on the agenda.
Write in: citycouncil@watsonville.gov (from the address this meeting's agenda gives for public comment)
Put "Public Comment" in the subject line and give the agenda item number and title in the body.
Official wording
APPROVE CONTRACT CHANGE ORDER NO. 12 WITH ROBERT A. BOTHMAN CONSTRUCTION FOR THE RAMSAY RENAISSANCE PROJECT (Recommended by Parks & Community Services Director Calubaquib) 1.Report - Ramsay Renaissance Bothman Construction CO 12.pdf 2.Resolution - Ramsay Renaissance Bothman Construction CCO 12.pdf 3.Change Order 12 - Bothman Construction Ramsay Renaissance Project.pdf RESOLUTION APPROVING CONTRACT CHANGE ORDER NUMBER 12, IN THE AMOUNT OF $266,100.50 WITH ROBERT A BOTHMAN CONSTRUCTION FOR THE RAMSAY PARK RENAISSANCE PROJECT, NO. PK-22-01, ADDING TO THE SCOPE OF WORK INCREASING THE CONTRACT AMOUNT BY $266,100.50 TO A REVISED CONTRACT AMOUNT NOT TO EXCEED $29,154,270.39
Summary written by claude-opus-5 from the agenda and the Report - Ramsay Renaissance Bothman Construction CO 12.pdf. It can contain mistakes. The official documents govern.