Watsonville City Council · Tuesday, December 1, 2026, 4:30 PM · Item 9.e · CONSENT AGENDA

NotableWater & utilities

Add $37,500 to design contract for Water Well No. 4 pump station

In plain English

The City Council is asked to approve a fourth change to its engineering contract with Luhdorff & Scalmanini Consulting Engineers, Inc. for the Water Well No. 4 Pump Station at the City's Roache Road location. The change adds $37,500 for continued engineering work through the end of construction, raising the total contract ceiling to $502,307, and pushes the contract end date from December 31, 2026 to June 30, 2027. A yes vote lets the City Manager sign the amendment, paid from the Water Enterprise Fund.

The well is meant to supplement Watsonville's aging wells and add a reliable source of drinking water, and the extra cost comes from the Water Enterprise Fund, the account funded by water ratepayers.

Key facts

  • Increases compensation by $37,500 for a revised total not to exceed $502,307.00
  • Extends the contract completion date from December 31, 2026 to June 30, 2027
  • Original contract approved March 10, 2020 (Resolution No. 30-20) for $434,088, with a December 31, 2021 expiration date
  • Prior changes: First Amendment added $30,719 (June 4, 2020); Second and Third Amendments were no-cost time extensions (2023 and 2024)
  • Funded by Water Enterprise Fund account 0720-913-7831-14557; staff states sufficient budget is available

Reasons to support

  • Staff say the project is in its final phases and the added scope is needed for the design engineer to support it through the end of construction.
  • Keeping the original design engineer is described by staff as the most efficient and effective way to finish the project.
  • The new well is intended to supplement the City's aging inventory of wells and add a reliable source of drinking water.

Reasons to oppose or change it

  • The contract has now grown from $434,088 to $502,307 and the deadline has moved four times since the original December 31, 2021 expiration, which raises questions about the original scope and schedule estimates.
  • The $37,500 comes from the Water Enterprise Fund, money collected for water service that then isn't available for other water system needs.
  • The staff report lists no alternatives considered, so Council is being asked to extend the same consultant rather than weigh another approach to finishing the remaining work.

Make your voice heard

Pick a side and we'll draft a short email to citycouncil@watsonville.gov that you can edit and send from your own account. Emails to the body become part of the public record.

How to take part

Show up: Tuesday, December 1, 2026 at 4:30 PM, City Council Chambers, 275 Main Street, Top Floor, Watsonville. California's open-meetings law (the Brown Act) gives you the right to speak on agenda items. Remote-participation links, when offered, are on the agenda.

Write in: citycouncil@watsonville.gov (from the address this meeting's agenda gives for public comment)

Put "Public Comment" in the subject line and give the agenda item number and title in the body.

Official wording

APPROVE FOURTH AMENDMENT TO DESIGN CONTRACT WITH LUHDORFF & SCALMANINI CONSULTING ENGINEERS, INC. FOR DESIGN SERVICES ON WATER WELL NO. 4 PUMP STATION (Recommended by Public Works & Utilities Director Green) 1.Report - 4th Amendment Luhdorff and Scalmanini Water Well No. 4 Pump Station.pdf 2.Resolution - 4th Amendment Luhdorff and Scalmanini Water Well No. 4 Pump Station.pdf 3.Contract - 4th Amendment Luhdorff and Scalmanini Water Well No. 4 Pump Station.pdf RESOLUTION APPROVING FOURTH AMENDMENT TO CONTRACT WITH LUHDORFF & SCALMANINI CONSULTING ENGINEERS, INC., FOR DESIGN SERVICES ON WATER WELL NO. 4 PUMP STATION; ADDING TO THE SCOPE OF WORK, INCREASING COMPENSATION BY THE AMOUNT OF $37,500 FOR A TOTAL CONTRACT AMOUNT NOT TO EXCEED $502,307; EXTENDING THE CONTRACT COMPLETION DATE FROM DECEMBER 31, 2026 TO JUNE 30, 2027; & AUTHORIZING & DIRECTING CITY MANAGER TO EXECUTE SAME (FUNDED BY THE WATER ENTERPRISE FUND [0720])