Watsonville City Council · Tuesday, November 10, 2026, 5:00 PM · Item 9.b · CONSENT AGENDA
$549,354 more for water line replacement on Beach, Union and Lincoln streets
In plain English
The City Council is asked to approve a final "balancing" change order with K.J. Woods Construction, Inc. for the water line replacement project on Beach St., Union St. and Lincoln St. (Project No. WA-25-14834). It would add $549,354.00, paid from the Water Enterprise Fund, bringing the total contract to $6,045,892.03. The extra money pays for work that turned out to be larger than the bid estimates: 16 more service lines than the 118 estimated, extra lengths of mostly 6-inch and 10-inch water line to route around unforeseen utility conflicts, and 31,218 additional square feet of paving. A yes vote lets the city pay the contractor for what was actually installed and close out the project.
The cost is covered by the Water Enterprise Fund, the account funded by water ratepayers, and staff would transfer money from the Chrom VI (hexavalent chromium) treatment project budget to cover it. Residents and businesses along Beach, Union and Lincoln streets get replaced water mains, new service lines and repaved street surface.
Key facts
- Change Order No. 4 adds $549,354.00, for a revised total contract amount of $6,045,892.03
- Original contract awarded July 8, 2025 by Resolution No. 186-25 (CM) at $4,938,000
- Cumulative increase from all four change orders is 22%
- Extra work includes 16 service lines beyond the 118 estimated and 31,218 additional square feet of paving, some required by Caltrans under its permit
- Funds come from Water Enterprise Fund account 072-913-7831-14834 after a transfer from account 0720-913-7855-14346, the Chrom VI Treatment capital project
Reasons to support
- The added quantities reflect work already installed in the ground — more service lines, more pipe to dodge utility conflicts, and paving over pavement that had deteriorated next to the trench — so the payment matches what was built.
- Staff states the change order is needed to finish and administratively close out the project, and that no reasonable alternative is known.
- Money is already available in the Water Enterprise Fund once transferred from the Chrom VI Treatment project, which is unlikely to spend its full fiscal-year budget because of bid timing.
Reasons to oppose or change it
- The contract has grown 22% above the $4,938,000 award through four change orders, raising questions about how closely the original bid quantities — such as 118 service lines versus the 134 actually needed — matched field conditions.
- The money is drawn from the Chrom VI Treatment capital project account, so a water-quality treatment project's budget is being tapped to cover pipeline cost overruns.
- The Lee Road boring under the railroad, added by Change Order No. 2 for $388,000, has been delayed by permit coordination issues and is still unfinished while the final balancing payment is approved.
Official wording
APPROVE CHANGE ORDER NO. 4 WITH K.J. WOODS CONSTRUCTION, INC., FOR THE WATER LINE REPLACEMENT PROJECT – BEACH ST., UNION ST., LINCOLN ST. (Recommended by Public Works & Utilities Director Green) 1.Report - KJ Woods Main Line Replacement Union Beach .pdf 2.Resolution - Main Line Replacement Beach Lincoln Union .pdf 3.CCO4 - KJ Woods Construction.pdf RESOLUTION APPROVING CHANGE ORDER NO. 4 WITH K.J. WOODS CONSTRUCTION, INC., FOR THE WATER LINE REPLACEMENT BEACH ST., UNION ST., LINCOLN ST. PROJECT, NO. WA-25-14834, IN THE AMOUNT OF $549,354.00 FROM THE WATER ENTERPRISE FUND FOR A REVISED TOTAL CONTRACT AMOUNT OF $6,045,892.03