Watsonville City Council · Tuesday, October 27, 2026, 5:00 PM · Item 6.r · CONSENT AGENDA

NotableWater & utilities

$284,476 more to design hexavalent chromium water treatment

In plain English

The City Council would approve a first amendment to its engineering design contract with Michael K. Nunley & Associates, Inc. for the Hexavalent Chromium Treatment Project. The amendment adds work to the scope and raises the firm's pay by $284,476, bringing the total contract to no more than $1,266,498. A yes vote also authorizes the City Manager to sign the amendment, with minor revisions allowed by the City Manager and City Attorney.

Hexavalent chromium is a contaminant in drinking water, and this contract pays for the engineering design of treatment facilities that Watsonville water customers will ultimately rely on and help fund; no construction is authorized by this item.

Key facts

  • The original design contract was awarded on December 2, 2025 by Resolution No. 308-25 (CM) in an amount not to exceed $982,022.
  • The amendment increases compensation by $284,476 for a total revised contract not to exceed $1,266,498 (one sentence in the resolution states the increase as $284,746).
  • The contractor is Michael K. Nunley & Associates, Inc., a corporation, providing engineering design services.
  • The item is listed on the consent agenda, recommended by Public Works & Utilities Director Green.
  • The resolution finds the action exempt from the California Environmental Quality Act under Guidelines Section 15378(b)(5), because approving a design contract is not a "project" that would physically change the environment; any environmental review for construction would come later when construction is brought to Council.

Reasons to support

  • Completing the design work is the step needed before a hexavalent chromium treatment project can be built, and the amendment adds scope the design requires.
  • Approving the amendment now keeps the existing design team on the job rather than restarting with a new engineering firm.
  • The action carries no environmental review burden, since it only funds design and any environmental analysis would be handled when construction comes to Council.

Reasons to oppose or change it

  • The increase is $284,476 on top of a contract awarded less than a year earlier, a roughly 29% jump in design cost before any construction contract has come to Council.
  • The resolution describes the change only as "adding to the scope of work," so Council members wanting the specific added tasks justified on the record would need to pull the item from the consent agenda, where items are approved together without separate discussion.
  • The resolution states the increase as $284,476 in its title and $284,746 in the body, a $270 discrepancy that a Council member may want corrected before signing.

Official wording

APPROVE FIRST CONTRACT AMENDMENT WITH MICHAEL K. NUNLEY & ASSOCIATES, INC., FOR THE DESIGN OF THE HEXAVALENT CHROMIUM TREATMENT PROJECT (Recommended by Public Works & Utilities Director Green) 1.Report - Cr6+ Treatment Design MKN Engineers.pdf 2.Resolution - Cr6+ Treatment Design MKN Engineers.pdf 3.Contract - MKN Engineers Amendment 1.pdf RESOLUTION APPROVING FIRST AMENDMENT TO CONTRACT WITH MICHAEL K. NUNLEY & ASSOCIATES, INC., FOR ENGINEERING DESIGN SERVICES FOR THE HEXAVALENT CHROMIUM TREATMENT PROJECT; ADDING TO THE SCOPE OF WORK, INCREASING COMPENSATION BY $284,476 FOR A TOTAL REVISED CONTRACT AMOUNT NOT TO EXCEED $1,266,498