MajorTransportation & traffic

Seek bids for $1.9 million Clifford Avenue repaving and traffic calming

In plain English

The City wants to repave and redesign about 2,200 feet of Clifford Avenue between Main Street and Pennsylvania Drive. Along with new pavement, the work would add wheelchair-accessible curb ramps, continuous striped bike lanes, narrower vehicle lanes, curb bulb-outs, new signs and striping, and all-way stop signs at both Montebello Drive intersections. Parking would be removed from one side of the street to make room. A yes vote approves the construction plans and lets the City advertise for contractor bids, with bids to be opened December 17, 2026.

People who live on and park along Clifford Avenue would lose parking on one side of the street, while drivers, walkers, cyclists and nearby schools would see new stop signs, bike lanes, accessible curb ramps and smoother pavement on a road many residents use to cross town.

Key facts

  • Engineer's estimated construction cost is $1,900,000: $850,000 in state Local Partnership Program funds, $160,000 in reprogrammed Regional Transportation Improvement Program funds, and $890,000 from the City's SB1 fund.
  • The project covers roughly 2,200 feet of Clifford Avenue between Main Street and Pennsylvania Drive; the 2024 Pavement Management Program Report projects a Pavement Condition Index of 56 ("fair") for this segment in 2026.
  • Bid opening is scheduled for December 17, 2026; construction is expected to begin April 15, 2027 and continue through summer 2027.
  • The contract must be awarded by March 26, 2027 or the City loses the $850,000 in Local Partnership Program funding.
  • A parking capacity and demand study by Traffic Patterns found parking would remain available on the corridor and surrounding streets, with no location expected to reach full capacity.

Reasons to support

  • Repaving now, while the pavement is still rated "fair" at a Pavement Condition Index of 56, avoids more extensive and costly repairs later on a heavily used cross-town route.
  • Outside money covers $1,010,000 of the $1,900,000 cost, and delaying the bid call risks missing the March 26, 2027 award deadline and forfeiting $850,000 in state Local Partnership Program funds.
  • Narrower lanes, curb bulb-outs, all-way stops at both Montebello Drive intersections, bike lanes and ADA-compliant curb ramps are intended to make the corridor safer and more accessible for pedestrians, cyclists and drivers near homes and schools.

Reasons to oppose or change it

  • Parking would be removed from one side of Clifford Avenue, pushing some residents and visitors to park farther away or on surrounding neighborhood streets, even though the study concludes spaces would still be available.
  • Narrower travel lanes and new all-way stops at both Montebello Drive intersections would slow a road the report describes as frequently used as an alternative route across town.
  • The City would commit $890,000 of its own SB1 road money to a street rated "fair" (PCI 56), money that is then unavailable for streets in worse condition.
  • Council could instead defer and direct staff to revise the design, but the report says that would delay construction and could cost the City the $850,000 state grant.

Official wording

APPROVE PLANS & SPECIFICATIONS & CALL FOR BIDS FOR THE CLIFFORD AVENUE ROAD REHABILITATION & TRAFFIC CALMING PROJECT (Recommended by Public Works & Utilities Director Green) 1.Report - Clifford Ave Road Improvements - Phase 1 Call Bids .pdf 2.1) Project Location Map.pdf 3.2) Clifford Ave Parking Capacity Study 2026.pdf 4.Resolution - Clifford Avenue Road Improvements - Phase 1.pdf RESOLUTION APPROVING PLANS & SPECIFICATIONS & CALLING FOR BIDS FOR THE CLIFFORD AVENUE ROAD IMPROVEMENTS - PHASE 1, PROJECT NO. ST-26-15268 (ENGINEER’S ESTIMATE OF $1,900,000 WILL BE FUNDED FROM THE STATE LOCAL PARTNERSHIP PROGRAM $850,000, SANTA CRUZ COUNTY REGIONAL TRANSPORTATION COMMISSION IMPROVEMENT PROGRAM $160,000, & THE SB1 TRANSPORTATION FUND $890,000)