Watsonville City Council · Tuesday, October 27, 2026, 5:00 PM · Item 6.v · CONSENT AGENDA
Appropriate $482,744 to finish Civic Center Library rooftop addition
In plain English
The Civic Center Library Rooftop Addition, built by Strawn Construction, Inc. under a contract the Council awarded on September 9, 2025, was supposed to finish by May 31, 2026, but rain and late delivery of construction materials pushed it back. The job is about 98 percent complete and is now expected to be done by November 30, 2026. A yes vote carries the unspent contract money forward into the 2026-2027 budget year \u2014 $346,572.25 in the Measure R Fund and $136,171.94 in the Library Fund \u2014 so the contractor can be paid for the remaining work.
Library users waiting on the new rooftop space are affected by the schedule slipping to November 30, 2026, and the vote keeps money already set aside for the job available to pay for the final 2 percent of construction.
Key facts
- Total project cost as originally appropriated: $3,009,383.43 \u2014 $2,600,000 from the Measure R Fund [0201] and $409,383.43 from the Library Fund [0250]
- Remaining encumbered contract balance: $452,744.19, plus an additional $30,000 appropriation to the Library Fund, for a total of $482,744.19
- Appropriations for Fiscal Year 2026-2027: $346,572.25 to Measure R Fund Account 974-7855-15220 and $136,171.94 to Library Fund Account 935-7855-15220
- Construction began October 2025 after a Notice to Proceed in September 2025; original completion date was May 31, 2026, revised to November 30, 2026
- The Council found on September 9, 2025 that the project is exempt from the California Environmental Quality Act under Guidelines Section 15378(b)(5)
Reasons to support
- The project is roughly 98 percent complete; without carrying the money into the new fiscal year, the City cannot pay for the final stretch of work.
- The delays came from rain and construction material delivery problems rather than new scope, and most of the $482,744.19 is money already committed under the Strawn Construction contract.
- The resolution lets the City Manager handle the remaining administrative and financial steps so the building can be finished by November 30, 2026.
Reasons to oppose or change it
- Beyond carrying forward the $452,744.19 already encumbered, the action adds a new $30,000 appropriation to the Library Fund \u2014 money that could otherwise stay available for other library needs.
- Measure R Fund dollars stay tied up in this project for another budget year instead of being freed for other uses the Council might fund.
- The completion date has slipped six months, from May 31, 2026 to November 30, 2026, and the item is on the consent agenda, meaning it would pass without discussion unless a Council member pulls it.
Official wording
APPROVE & APPROPRIATE ENCUMBERED FUNDS FOR THE CIVIC CENTER LIBRARY ROOFTOP ADDITION (Recommended by Library Director Martinez) 1.Report - Appropriation for Civic Center Library Rooftop Addition.pdf 2.Resolution - Appropriation for Civic Center Library Rooftop Addition CB-25-5220.pdf RESOLUTION AUTHORIZING THE APPROPRIATION OF FUNDS FOR THE COMPLETION OF THE CIVIC CENTER LIBRARY ROOFTOP ADDITION, NO. CB-25-5220, TO THE MEASURE R FUND [0201], IN THE AMOUNT OF $346,572.25 & TO THE LIBRARY FUND [0250], IN THE AMOUNT OF $136,171.94 FOR FISCAL YEAR 2026-2027